CDM 2007 workers
For information about the role of workers under the 2015 CDM regulations see CDM 2015 workers.
The text below relates to the superseded 2007 CDM regulations and is provided as a historical reference.
Contents |
[edit] Introduction
The Construction (Design and Management) Regulations (CDM Regulations) are intended to ensure that health and safety issues are properly considered during a project’s development so that the risk of harm to those who have to build, use and maintain structures is reduced.
The regulations apply from concept design onward and impose duties on:
- The client.
- Designers.
- The CDM co-ordinator.
- The principal contractor.
- Contractors.
- Workers (including the self-employed).
The CDM Regulations describe a construction site as …any place where construction work is being carried out or to which the workers have access, but does not include a workplace within it which is set aside for purposes other than construction work.
It is not entirely clear from the regulations that there are specific duties imposed on workers, other than those imposed on ‘every person’ or ‘every duty holder’ however, they do impose duties on employers, contractors and principal contractors in relation to workers that by implication require worker engagement.
(The requirements below are only those that relate to workers, for other requirements, refer to specific articles about those duty holders)
[edit] Every person
- Every person concerned in a project who is working under the control of another person shall report to that person anything which he is aware is likely to endanger the health or safety of himself or others.
- Every person at work on a construction site shall, so far as is reasonably practicable, be instructed in the correct use of any fire-fighting equipment which it may be necessary for him to use.
[edit] Every duty holder
- Shall not accept an appointment or engagement unless he is competent.
- Shall co-operate and co-ordinate work to ensure the health and safety of construction workers and others who may be affected by the work.
- Shall apply the general principles of prevention.
- Shall not arrange for or instruct a worker unless the worker is competent, or under the supervision of a competent person.
[edit] Contractor
Shall provide suitable information and training, including:
- Site induction (where not provided by the principal contractor).
- Information about risks to their health and safety.
- Measures identified in risk assessments.
- Site rules.
- Procedures to be followed in the event of serious and imminent danger, and the identity of persons nominated to implement those procedures.
They should also provide their own employees with health and safety training.
[edit] Principal contractor
- Shall facilitate co-operation and co-ordination between all parties on site.
- Provide welfare facilities.
- Draw up rules which are appropriate to the construction site.
- Consult with workers or their representatives before making health and safety decisions.
- Ensure that notifiable details are displayed where they can be read by workers.
- Provide a suitable site induction.
- Provide information and training for the particular work to be carried out.
- Ensure that workers or their representatives can inspect and take copies of information which relates to the planning and management of the project.
[edit] Other measures
- Cofferdams and caissons shall be appropriately equipped so that workers can gain shelter or escape if water or materials enter it.
- Changing rooms shall be provided if necessary.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
CIOB Apprentice of the Year 2025/26
Construction apprentice from Lincoln Mia Owen wins this years title.
Insulation solutions with less waste for a circular economy
Rob Firman, Technical and Specification Manager, Polyfoam XPS explains.
Recycled waste plastic in construction
Hierarchy, prevention to disposal, plastic types and approaches.
UK Net Zero Carbon Buildings Standard V1 published
Free-to-access technical standard to enable robust proof of a decarbonising built environment.
Prostate Cancer Awareness Month
Why talking about prostate cancer matters in construction.
The Architectural Technology podcast: Where it's AT
Catch up for free, subscribe and share with your network.
The Association of Consultant Architects recap
A reintroduction and recap of ACA President; Patrick Inglis' Autumn update.
The Home Energy Model and its wrappers
From SAP to HEM, EPC for MEES and FHS assessment wrappers.
Future Homes Standard Essentials launched
Future Homes Hub launches new campaign to help sector prepare for the implementation of new building standards.
Building Safety recap February, 2026
Our regular run-down of key building safety related events of the month.
Planning reform: draft NPPF and industry responses.
Last chance to comment on proposed changes to the NPPF.
A Regency palace of colour and sensation. Book review.
Delayed, derailed and devalued
How the UK’s planning crisis is undermining British manufacturing.
How much does it cost to build a house?
A brief run down of key considerations from a London based practice.
The need for a National construction careers campaign
Highlighted by CIOB to cut unemployment, reduce skills gap and deliver on housing and infrastructure ambitions.